Define the use before defining the finishes
Start with what the business will do in the space, the people it serves, equipment needs and how staff and visitors will move through it. A cosmetic refresh, a first build-out and a change in use can involve different design and review paths. The current condition of the space is as important as the desired finished appearance.
Collect available plans and ask the landlord for building standards and known system information. Document which assumptions still need confirmation by the design team or responsible trades.
Build a responsibility list
Clarify who decides, who supplies information and who pays for each part of the work. The list should include the tenant, property owner, property manager, architect or designer, contractor and separately engaged specialists. Review the lease work letter and improvement requirements with the appropriate advisers.
- Landlord approvals and building rules.
- Design documents and technical responses.
- Owner-supplied equipment and finish selections.
- Permitting and agency communications.
- Shared-system access and shutdown coordination.
- Construction, inspections and final handoff.
Work backward from your operating goal
Opening dates often involve more than construction duration. Design completion, landlord review, permitting, material procurement and equipment delivery can all influence the sequence. Separate a business target from the dates that have actually been confirmed.
For an occupied space, define the areas that must remain usable, delivery routes, noise-sensitive hours and any planned service interruptions. After-hours work or multiple phases should be addressed in the pricing assumptions.
Check the local permit path
Seattle describes tenant improvements within its addition and alteration permit guidance. Bellevue distinguishes tenant improvements from initial build-outs or changes of use in its commercial TI guidance. Bellevue also identifies separate permits for certain building systems and signage. Confirm requirements for the address and scope with the jurisdiction and your design team.
JMD can provide independent permit coordination if you already have your construction team. Coordination supports application organization and review responses; it does not determine an agency’s approval or issuance date.
Make the proposal and closeout scope readable
List inclusions, exclusions, allowances, owner-supplied items, access assumptions and the process for changes. At the end of the work, clarify the walkthrough, punch list and documents to be handed over. Discuss the applicable inspection and occupancy steps with the responsible professionals before planning use of the renovated space.
For a commercial tenant-improvement proposal, share the address, existing and proposed use, approximate area, drawings, landlord requirements, target timing and budget range.